Construction progress
JVC · Iman Developers L.L.C
DLD first inspected the site on Dec 22, 2021 at 20.3% complete, and recorded it as finished after 5 inspections, the last on May 15, 2023.
May 15, 2023
6 months after the previous inspection
3 months after the previous inspection
4 months after the previous inspection
4 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 2321), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.