One Residence at Downtown Dubai

Construction progress

One Residence at Downtown Dubai construction updates

Downtown Dubai · Ginco Properties L.L.C

Under constructionLast site inspection July 27, 2026 · 3 months ago
6.3%complete

When DLD first inspected the site on Jun 21, 2024, it was 0% complete. After 5 inspections it now stands at 6.3%.

That is about 0.3% more of the building completed each month on average.

First inspection · 0%Latest · 6.3%
Construction started
October 1, 2024
Completion date registered with DLD
March 31, 2027
Site inspections
5
Units
458
Escrow bank
Emirates Islamic Bank P.J.S.C.
DLD project no.
3150

Latest site photos

July 27, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. July 27, 2026

    6 months after the previous inspection

    +0.3%6.3%
  2. February 9, 2026

    3 months after the previous inspection

    +1.7%6%
  3. October 27, 2025

    5 months after the previous inspection

    +2.9%4.3%
  4. May 19, 2025

    11 months after the previous inspection

    +1.3%1.3%
  5. June 21, 2024

    First inspection

    0%

Thinking about One Residence at Downtown Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3150), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.