Under constructionLast site inspection September 22, 2026 · 2 months ago
20.1%complete

When DLD first inspected the site on Nov 12, 2024, it was 0% complete. After 5 inspections it now stands at 20.1%.

That is about 0.9% more of the building completed each month on average.

First inspection · 0%Latest · 20.1%
Construction started
January 1, 2025
Completion date registered with DLD
June 30, 2028
Site inspections
5
Units
269
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
3366

Latest site photos

September 22, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 22, 2026

    2 months after the previous inspection

    +2.9%20.1%
  2. August 6, 2026

    7 months after the previous inspection

    +10.7%17.1%
  3. January 14, 2026

    3 months after the previous inspection

    +1.7%6.4%
  4. October 7, 2025

    11 months after the previous inspection

    +4.7%4.7%
  5. November 12, 2024

    First inspection

    0%

Thinking about One Park Square at JVC by Iman Developers?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3366), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat