One Park Central at JVC

Construction progress

One Park Central at JVC construction updates

JVC · Iman Developers L.L.C

Under constructionLast site inspection October 28, 2026 · 10 days ago
32.3%complete

When DLD first inspected the site on Mar 1, 2024, it was 0% complete. After 6 inspections it now stands at 32.3%.

That is about 1% more of the building completed each month on average.

First inspection · 0%Latest · 32.3%
Construction started
April 25, 2024
Completion date registered with DLD
June 30, 2027
Site inspections
6
Units
526
Escrow bank
Mashreq Bank Psc
DLD project no.
2969

Latest site photos

October 28, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 28, 2026

    8 months after the previous inspection

    +12.2%32.3%
  2. March 11, 2026

    3 months after the previous inspection

    +8%20.1%
  3. December 24, 2025

    7 months after the previous inspection

    +6%12.1%
  4. May 27, 2025

    5 months after the previous inspection

    +3.1%6.1%
  5. December 23, 2024

    10 months after the previous inspection

    +3.1%3.1%
  6. March 1, 2024

    First inspection

    0%

Thinking about One Park Central at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2969), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.