Onda by Kasco at Business Bay Dubai

Construction progress

Onda by Kasco at Business Bay Dubai construction updates

Business Bay · Kasco Real Estate Development L.L.C

Under constructionLast site inspection August 19, 2026 · 3 months ago
61.1%complete

When DLD first inspected the site on May 10, 2024, it was 0% complete. After 7 inspections it now stands at 61.1%.

That is about 2.2% more of the building completed each month on average.

First inspection · 0%Latest · 61.1%
Construction started
September 1, 2024
Completion date registered with DLD
August 31, 2027
Site inspections
7
Units
352
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
3052

Latest site photos

August 19, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 19, 2026

    3 months after the previous inspection

    +9.6%61.1%
  2. May 7, 2026

    3 months after the previous inspection

    +15.8%51.5%
  3. January 29, 2026

    4 months after the previous inspection

    +15.1%35.7%
  4. September 15, 2025

    4 months after the previous inspection

    +6.3%20.5%
  5. May 28, 2025

    3 months after the previous inspection

    +5.7%14.2%
  6. February 12, 2025

    9 months after the previous inspection

    +8.6%8.6%
  7. May 10, 2024

    First inspection

    0%

Thinking about Onda by Kasco at Business Bay Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3052), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.