Oceanz 2 by Danube at Dubai Maritime City

Construction progress

Oceanz 2 by Danube at Dubai Maritime City construction updates

Dubai Maritime City · Danube Properties Development L.L.C

Under constructionLast site inspection August 25, 2026 · 2 months ago
42%complete

When DLD first inspected the site on Oct 24, 2023, it was 0% complete. After 9 inspections it now stands at 42%.

That is about 1.2% more of the building completed each month on average.

First inspection · 0%Latest · 42%
Construction started
March 1, 2024
Site inspections
9
Units
781
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2756

Latest site photos

August 25, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. August 25, 2026

    4 months after the previous inspection

    +12.4%42%
  2. May 7, 2026

    4 months after the previous inspection

    +8.6%29.6%
  3. December 24, 2025

    3 months after the previous inspection

    +5.7%21%
  4. October 1, 2025

    4 months after the previous inspection

    +5%15.3%
  5. June 16, 2025

    5 months after the previous inspection

    +0.6%10.2%
  6. January 18, 2025

    5 months after the previous inspection

    +6.4%9.6%
  7. August 8, 2024

    4 months after the previous inspection

    +2.5%3.3%
  8. April 23, 2024

    6 months after the previous inspection

    +0.7%0.7%
  9. October 24, 2023

    First inspection

    0%

Thinking about Oceanz 2 by Danube at Dubai Maritime City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2756), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.