Oasiz 2 by Danube at Dubai Silicon Oasis

Construction progress

Oasiz 2 by Danube at Dubai Silicon Oasis construction updates

Dubai Silicon Oasis · Danube Properties Development L.L.C

Under constructionLast site inspection July 29, 2026 · 3 months ago
31%complete

When DLD first inspected the site on Sep 3, 2024, it was 0% complete. After 6 inspections it now stands at 31%.

That is about 1.4% more of the building completed each month on average.

First inspection · 0%Latest · 31%
Construction started
December 1, 2024
Completion date registered with DLD
November 30, 2027
Site inspections
6
Units
483
Escrow bank
Ajman Bank /P.J.S.C
DLD project no.
3260

Latest site photos

July 29, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. July 29, 2026

    3 months after the previous inspection

    +12.5%31%
  2. April 15, 2026

    4 months after the previous inspection

    +6.5%18.5%
  3. December 24, 2025

    3 months after the previous inspection

    +6.7%12%
  4. September 16, 2025

    3 months after the previous inspection

    +3.5%5.3%
  5. June 3, 2025

    9 months after the previous inspection

    +1.8%1.8%
  6. September 3, 2024

    First inspection

    0%

Thinking about Oasiz 2 by Danube at Dubai Silicon Oasis?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3260), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.