Muraba Veil at Al Wasl, Jumeirah Dubai

Construction progress

Muraba Veil at Al Wasl, Jumeirah Dubai construction updates

Al Wasl Dubai · Muraba Properties L.L.C

Under constructionLast site inspection September 28, 2026 · 40 days ago
7.6%complete

When DLD first inspected the site on May 23, 2024, it was 0% complete. After 9 inspections it now stands at 7.6%.

That is about 0.3% more of the building completed each month on average.

First inspection · 0%Latest · 7.6%
Construction started
December 1, 2024
Completion date registered with DLD
December 31, 2028
Site inspections
9
Units
135
Escrow bank
Commercial Bank Of Dubai(Psc)
DLD project no.
3106

Latest site photos

September 28, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 28, 2026

    11 days after the previous inspection

    +0.1%7.6%
  2. September 17, 2026

    3 months after the previous inspection

    +0.3%7.5%
  3. June 18, 2026

    3 months after the previous inspection

    +1.7%7.2%
  4. March 16, 2026

    4 months after the previous inspection

    +4.4%5.5%
  5. November 5, 2025

    34 days after the previous inspection

    +0.4%1.1%
  6. October 2, 2025

    4 months after the previous inspection

    +0.3%0.7%
  7. June 16, 2025

    2 months after the previous inspection

    +0.4%0.4%
  8. May 1, 2025

    11 months after the previous inspection

    0%
  9. May 23, 2024

    First inspection

    0%

Thinking about Muraba Veil at Al Wasl, Jumeirah Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3106), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.