Construction progress
Al Furjan · Januss Real Estate Developers L.L.C
When DLD first inspected the site on May 9, 2024, it was 0% complete. After 8 inspections it now stands at 51.2%.
That is about 2% more of the building completed each month on average.
July 6, 2026
4 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
7 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 3047), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.