Minati Homes 1 at Al Furjan Dubai

Construction progress

Minati Homes 1 at Al Furjan Dubai construction updates

Al Furjan · Januss Real Estate Developers L.L.C

Under constructionLast site inspection July 6, 2026 · 4 months ago
51.2%complete

When DLD first inspected the site on May 9, 2024, it was 0% complete. After 8 inspections it now stands at 51.2%.

That is about 2% more of the building completed each month on average.

First inspection · 0%Latest · 51.2%
Construction started
April 29, 2024
Completion date registered with DLD
September 30, 2026
Site inspections
8
Units
82
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3047

Latest site photos

July 6, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. July 6, 2026

    4 months after the previous inspection

    +7.9%51.2%
  2. March 19, 2026

    3 months after the previous inspection

    +4.9%43.4%
  3. December 17, 2025

    3 months after the previous inspection

    +9.1%38.5%
  4. September 24, 2025

    3 months after the previous inspection

    +9.6%29.3%
  5. June 11, 2025

    3 months after the previous inspection

    +10.1%19.7%
  6. February 26, 2025

    3 months after the previous inspection

    +6.5%9.6%
  7. November 29, 2024

    7 months after the previous inspection

    +3.1%3.1%
  8. May 9, 2024

    First inspection

    0%

Thinking about Minati Homes 1 at Al Furjan Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3047), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.