Milestone Residences at Jumeirah Village Triangle

Construction progress

Milestone Residences at Jumeirah Village Triangle construction updates

JVT · Axiom Prime Real Estate Development L.L.C

CompletedLast site inspection February 4, 2026 · 9 months ago
100%complete

DLD first inspected the site on Apr 5, 2024 at 0% complete, and recorded it as finished after 6 inspections, the last on Feb 4, 2026.

First inspection · 0%Latest · 100%
Construction started
April 15, 2024
Completion date registered with DLD
March 13, 2026
Site inspections
6
Units
53
Escrow bank
Mashreq Bank Psc
DLD project no.
3015

Latest site photos

February 4, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. February 4, 2026

    7 months after the previous inspection

    +30.5%100%
  2. July 7, 2025

    38 days after the previous inspection

    +17.1%69.5%
  3. May 30, 2025

    2 months after the previous inspection

    +16.4%52.4%
  4. April 11, 2025

    2 months after the previous inspection

    +12.3%36%
  5. February 13, 2025

    10 months after the previous inspection

    +23.8%23.8%
  6. April 5, 2024

    First inspection

    0%

Thinking about Milestone Residences at Jumeirah Village Triangle?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3015), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.