Construction progress
JVC · London Gate Real Estate Development L.L.C
When DLD first inspected the site on Aug 14, 2025, it was 19.1% complete. After 2 inspections it now stands at 19.1%.
April 21, 2026
8 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 3647), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.