MI Casa by London Gate at JVC, Dubai

Construction progress

MI Casa by London Gate at JVC, Dubai construction updates

JVC · London Gate Real Estate Development L.L.C

Under constructionLast site inspection April 21, 2026 · 7 months ago
19.1%complete

When DLD first inspected the site on Aug 14, 2025, it was 19.1% complete. After 2 inspections it now stands at 19.1%.

First inspection · 19.1%Latest · 19.1%
Construction started
October 27, 2025
Completion date registered with DLD
October 26, 2028
Site inspections
2
Units
76
Escrow bank
Abu Dhabi Islamic Bank
DLD project no.
3647

Latest site photos

April 21, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. April 21, 2026

    8 months after the previous inspection

    19.1%
  2. August 14, 2025

    First inspection

    19.1%

Thinking about MI Casa by London Gate at JVC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3647), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat