MBL Signature at JLT, Dubai

Construction progress

MBL Signature at JLT, Dubai construction updates

JLT · Mag 10 Property Development Dmcc

Under constructionLast site inspection May 6, 2026 · 6 months ago
60.1%complete

When DLD first inspected the site on Jun 11, 2025, it was 35.4% complete. After 3 inspections it now stands at 60.1%.

That is about 2.3% more of the building completed each month on average.

First inspection · 35.4%Latest · 60.1%
Construction started
May 2, 2025
Completion date registered with DLD
March 31, 2027
Site inspections
3
Units
463
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
3780

Latest site photos

May 6, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. May 6, 2026

    4 months after the previous inspection

    +17%60.1%
  2. December 24, 2025

    6 months after the previous inspection

    +7.7%43.1%
  3. June 11, 2025

    First inspection

    35.4%

Thinking about MBL Signature at JLT, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3780), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.