MAYA 5 at Jumeirah Village Triangle Dubai

Construction progress

MAYA 5 at Jumeirah Village Triangle Dubai construction updates

JVT · London Gate Real Estate Development L.L.C

CompletedLast site inspection November 22, 2024 · 2 years ago
100%complete

DLD first inspected the site on Sep 26, 2023 at 31.6% complete, and recorded it as finished after 4 inspections, the last on Nov 22, 2024.

First inspection · 31.6%Latest · 100%
Construction started
October 15, 2022
Completion date registered with DLD
October 15, 2024
Site inspections
4
Units
59
Escrow bank
Commercial Bank Of Dubai(Psc)
DLD project no.
2747

Latest site photos

November 22, 2024

Progress over time

Progress over time
0%25%50%75%100%2024

Inspection history

  1. November 22, 2024

    3 months after the previous inspection

    +2.9%100%
  2. August 13, 2024

    5 months after the previous inspection

    +33.2%97.1%
  3. March 1, 2024

    5 months after the previous inspection

    +32.3%63.8%
  4. September 26, 2023

    First inspection

    31.6%

Thinking about MAYA 5 at Jumeirah Village Triangle Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2747), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.