Marwa Heights at JVC

Construction progress

Marwa Heights at JVC construction updates

JVC · New World Developments L.L.C

CompletedLast site inspection July 12, 2023 · 3 years ago
100%complete

DLD first inspected the site on Feb 7, 2019 at 23.6% complete, and recorded it as finished after 5 inspections, the last on Jul 12, 2023.

First inspection · 23.6%Latest · 100%
Construction started
July 12, 2017
Completion date registered with DLD
July 12, 2023
Site inspections
5
Units
128
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2062

Latest site photos

July 12, 2023

Progress over time

Progress over time
0%25%50%75%100%2020202120222023

Inspection history

  1. July 12, 2023

    11 months after the previous inspection

    +4.8%100%
  2. August 2, 2022

    6 months after the previous inspection

    +7.1%95.2%
  3. February 8, 2022

    9 months after the previous inspection

    +32.5%88.1%
  4. May 9, 2021

    27 months after the previous inspection

    +32%55.6%
  5. February 7, 2019

    First inspection

    23.6%

Thinking about Marwa Heights at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2062), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.