Construction progress
Arjan Dubai · Marquis Circle Real Estate Developer L.L.C
DLD first inspected the site on Aug 7, 2023 at 0% complete, and recorded it as finished after 6 inspections, the last on Sep 2, 2026.
September 2, 2026
6 months after the previous inspection
4 months after the previous inspection
6 months after the previous inspection
6 months after the previous inspection
14 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 2739), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.