Marina Cove by Emaar at Dubai Marina

Construction progress

Marina Cove by Emaar at Dubai Marina construction updates

Dubai Marina · Emaar Development P.J.S.C.

Under constructionLast site inspection October 1, 2026 · 37 days ago
5.7%complete

When DLD first inspected the site on Oct 8, 2024, it was 0% complete. After 4 inspections it now stands at 5.7%.

That is about 0.2% more of the building completed each month on average.

First inspection · 0%Latest · 5.7%
Construction started
October 30, 2024
Completion date registered with DLD
September 30, 2029
Site inspections
4
Units
227
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
3328

Latest site photos

October 1, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 1, 2026

    6 months after the previous inspection

    +4.9%5.7%
  2. March 25, 2026

    0 days after the previous inspection

    0.8%
  3. March 25, 2026

    18 months after the previous inspection

    +0.8%0.8%
  4. October 8, 2024

    First inspection

    0%

Thinking about Marina Cove by Emaar at Dubai Marina?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3328), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat