Mar Casa by Deyaar at Dubai Maritime City

Construction progress

Mar Casa by Deyaar at Dubai Maritime City construction updates

Dubai Maritime City · Deyaar Development (P.J.S.C)

Under constructionLast site inspection October 29, 2026 · 9 days ago
66.8%complete

When DLD first inspected the site on Mar 1, 2023, it was 0% complete. After 9 inspections it now stands at 66.8%.

That is about 1.5% more of the building completed each month on average.

First inspection · 0%Latest · 66.8%
Construction started
September 1, 2023
Completion date registered with DLD
October 31, 2026
Site inspections
9
Units
585
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2589

Latest site photos

October 29, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. October 29, 2026

    3 months after the previous inspection

    +10.3%66.8%
  2. August 4, 2026

    3 months after the previous inspection

    +8.2%56.5%
  3. May 4, 2026

    4 months after the previous inspection

    +14.2%48.2%
  4. December 22, 2025

    0 days after the previous inspection

    34%
  5. December 22, 2025

    6 months after the previous inspection

    +13.7%34%
  6. June 11, 2025

    5 months after the previous inspection

    +5.4%20.3%
  7. January 2, 2025

    10 months after the previous inspection

    +10%15%
  8. March 8, 2024

    12 months after the previous inspection

    +4.9%4.9%
  9. March 1, 2023

    First inspection

    0%

Thinking about Mar Casa by Deyaar at Dubai Maritime City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2589), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.