Maison Elysee 3 at JVC, Dubai

Construction progress

Maison Elysee 3 at JVC, Dubai construction updates

JVC · Pantheon Elysee Real Estate Development L.L.C

Under constructionLast site inspection June 25, 2026 · 4 months ago
4.4%complete

When DLD first inspected the site on Oct 11, 2024, it was 0% complete. After 5 inspections it now stands at 4.4%.

That is about 0.2% more of the building completed each month on average.

First inspection · 0%Latest · 4.4%
Construction started
November 1, 2024
Completion date registered with DLD
October 31, 2027
Site inspections
5
Units
379
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
3281

Latest site photos

June 25, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. June 25, 2026

    3 months after the previous inspection

    +0.8%4.4%
  2. March 31, 2026

    5 months after the previous inspection

    +1.3%3.6%
  3. November 10, 2025

    6 months after the previous inspection

    +2.1%2.3%
  4. May 13, 2025

    7 months after the previous inspection

    +0.2%0.2%
  5. October 11, 2024

    First inspection

    0%

Thinking about Maison Elysee 3 at JVC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3281), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.