Maimoon Gardens at JVC Dubai

Construction progress

Maimoon Gardens at JVC Dubai construction updates

JVC · Fakhruddin Properties Development L.L.C

Under constructionLast site inspection August 13, 2026 · 3 months ago
78%complete

When DLD first inspected the site on Feb 8, 2023, it was 2% complete. After 10 inspections it now stands at 78%.

That is about 1.8% more of the building completed each month on average.

First inspection · 2%Latest · 78%
Construction started
December 1, 2022
Completion date registered with DLD
December 31, 2025
Site inspections
10
Units
722
Buildings
3
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2412

Latest site photos

August 13, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. August 13, 2026

    3 months after the previous inspection

    +14.6%78%
  2. May 13, 2026

    4 months after the previous inspection

    +5.3%63.5%
  3. January 22, 2026

    3 months after the previous inspection

    +15.9%58.2%
  4. October 9, 2025

    8 months after the previous inspection

    +12.1%42.2%
  5. February 20, 2025

    4 months after the previous inspection

    +7.7%30.1%
  6. October 21, 2024

    3 months after the previous inspection

    +4.4%22.4%
  7. July 17, 2024

    8 months after the previous inspection

    +9.8%18%
  8. November 21, 2023

    5 months after the previous inspection

    +1.9%8.2%
  9. June 14, 2023

    4 months after the previous inspection

    +4.3%6.3%
  10. February 8, 2023

    First inspection

    2%

Thinking about Maimoon Gardens at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2412), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.