Maha Townhouses by Nshama

Construction progress

Maha Townhouses by Nshama construction updates

Town Square · Nshama Properties Owned By Nshmi Development One Person Company L.L.C

CompletedLast site inspection May 9, 2025 · last year
100%complete

DLD first inspected the site on Oct 18, 2022 at 0% complete, and recorded it as finished after 10 inspections, the last on May 9, 2025.

First inspection · 0%Latest · 100%
Construction started
March 1, 2023
Completion date registered with DLD
August 31, 2025
Site inspections
10
Units
501
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2490

Latest site photos

May 9, 2025

Progress over time

Progress over time
0%25%50%75%100%202320242025

Inspection history

  1. May 9, 2025

    4 days after the previous inspection

    100%
  2. May 5, 2025

    4 months after the previous inspection

    +12.9%100%
  3. January 8, 2025

    2 months after the previous inspection

    +7%87.1%
  4. October 29, 2024

    4 months after the previous inspection

    +20%80.1%
  5. July 1, 2024

    21 days after the previous inspection

    +5.3%60.1%
  6. June 10, 2024

    2 months after the previous inspection

    +19.8%54.8%
  7. March 26, 2024

    6 months after the previous inspection

    +28.1%35%
  8. October 5, 2023

    5 months after the previous inspection

    +6.7%7%
  9. April 25, 2023

    6 months after the previous inspection

    +0.3%0.3%
  10. October 18, 2022

    First inspection

    0%

Thinking about Maha Townhouses by Nshama?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2490), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.