Luma22 at JVC Dubai

Construction progress

Luma22 at JVC Dubai construction updates

JVC · Townx Real Estate Development L.L.C

CompletedLast site inspection August 2, 2024 · 2 years ago
100%complete

DLD first inspected the site on Nov 29, 2022 at 0% complete, and recorded it as finished after 6 inspections, the last on Aug 2, 2024.

First inspection · 0%Latest · 100%
Construction started
December 1, 2022
Completion date registered with DLD
September 30, 2024
Site inspections
6
Units
407
Buildings
2
Escrow bank
Commercial Bank Of Dubai(Psc)
DLD project no.
2518

Latest site photos

August 2, 2024

Progress over time

Progress over time
0%25%50%75%100%20232024

Inspection history

  1. August 2, 2024

    4 months after the previous inspection

    +19.9%100%
  2. March 28, 2024

    4 months after the previous inspection

    +27.2%80.1%
  3. November 27, 2023

    3 months after the previous inspection

    +22.7%52.9%
  4. September 11, 2023

    3 months after the previous inspection

    +19.1%30.1%
  5. June 14, 2023

    6 months after the previous inspection

    +11%11%
  6. November 29, 2022

    First inspection

    0%

Thinking about Luma22 at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2518), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat