Luma21 at JVC Dubai

Construction progress

Luma21 at JVC Dubai construction updates

JVC · Townx Real Estate Development L.L.C

CompletedLast site inspection February 22, 2023 · 4 years ago
100%complete

DLD first inspected the site on Dec 6, 2021 at 10% complete, and recorded it as finished after 5 inspections, the last on Feb 22, 2023.

First inspection · 10%Latest · 100%
Construction started
July 25, 2021
Completion date registered with DLD
April 30, 2023
Site inspections
5
Units
238
Escrow bank
Commercial Bank Of Dubai(Psc)
DLD project no.
2327

Latest site photos

February 22, 2023

Progress over time

Progress over time
0%25%50%75%100%20222023

Inspection history

  1. February 22, 2023

    4 months after the previous inspection

    +13.9%100%
  2. October 18, 2022

    4 months after the previous inspection

    +30.9%86.1%
  3. June 15, 2022

    3 months after the previous inspection

    +20.1%55.2%
  4. March 22, 2022

    3 months after the previous inspection

    +25.2%35.2%
  5. December 6, 2021

    First inspection

    10%

Thinking about Luma21 at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2327), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.