Lucky Oasis Residence at JVC

Construction progress

Lucky Oasis Residence at JVC construction updates

JVC · Lucky Aeon Real Estate Development

Under constructionLast site inspection May 7, 2026 · 6 months ago
20%complete

When DLD first inspected the site on Jan 12, 2024, it was 0% complete. After 4 inspections it now stands at 20%.

That is about 0.7% more of the building completed each month on average.

First inspection · 0%Latest · 20%
Construction started
June 1, 2024
Completion date registered with DLD
June 30, 2026
Site inspections
4
Units
144
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2888

Latest site photos

May 7, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. May 7, 2026

    3 months after the previous inspection

    +5.4%20%
  2. January 27, 2026

    7 months after the previous inspection

    +6%14.6%
  3. June 18, 2025

    17 months after the previous inspection

    +8.6%8.6%
  4. January 12, 2024

    First inspection

    0%

Thinking about Lucky Oasis Residence at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2888), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.