Livel Residenza at JVC Dubai

Construction progress

Livel Residenza at JVC Dubai construction updates

JVC · Vantage Capital Real Estate Development L.L.C

Under constructionLast site inspection July 15, 2026 · 4 months ago
20%complete

When DLD first inspected the site on Jun 27, 2024, it was 10.3% complete. After 3 inspections it now stands at 20%.

That is about 0.4% more of the building completed each month on average.

First inspection · 10.3%Latest · 20%
Construction started
January 30, 2025
Completion date registered with DLD
December 31, 2026
Site inspections
3
Units
137
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
3072

Latest site photos

July 15, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. July 15, 2026

    13 months after the previous inspection

    +4.2%20%
  2. June 23, 2025

    12 months after the previous inspection

    +5.6%15.9%
  3. June 27, 2024

    First inspection

    10.3%

Thinking about Livel Residenza at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3072), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.