Lincoln Star Residence At Dubai South

Construction progress

Lincoln Star Residence At Dubai South construction updates

Dubai South · Lincoln Star Real Estate Development L.L.C

Under constructionLast site inspection October 27, 2026 · 11 days ago
55.4%complete

When DLD first inspected the site on May 28, 2024, it was 0% complete. After 5 inspections it now stands at 55.4%.

That is about 1.9% more of the building completed each month on average.

First inspection · 0%Latest · 55.4%
Construction started
October 1, 2024
Completion date registered with DLD
September 30, 2026
Site inspections
5
Units
48
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
3102

Latest site photos

October 27, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 27, 2026

    8 months after the previous inspection

    +8.2%55.4%
  2. February 26, 2026

    5 months after the previous inspection

    +16.6%47.2%
  3. October 6, 2025

    6 months after the previous inspection

    +13.5%30.6%
  4. April 21, 2025

    11 months after the previous inspection

    +17.1%17.1%
  5. May 28, 2024

    First inspection

    0%

Thinking about Lincoln Star Residence At Dubai South?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3102), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.