Lexington by Nshama at Town Square

Construction progress

Lexington by Nshama at Town Square construction updates

Town Square · Nshama Properties Owned By Nshmi Development One Person Company L.L.C

Under constructionLast site inspection August 13, 2026 · 3 months ago
4.5%complete

When DLD first inspected the site on Oct 30, 2024, it was 0% complete. After 4 inspections it now stands at 4.5%.

That is about 0.2% more of the building completed each month on average.

First inspection · 0%Latest · 4.5%
Construction started
May 5, 2025
Completion date registered with DLD
September 30, 2027
Site inspections
4
Units
142
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3364

Latest site photos

August 13, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 13, 2026

    6 months after the previous inspection

    +4.5%4.5%
  2. February 3, 2026

    0 days after the previous inspection

    0%
  3. February 3, 2026

    15 months after the previous inspection

    +0%0%
  4. October 30, 2024

    First inspection

    0%

Thinking about Lexington by Nshama at Town Square?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3364), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat