Legado at JVC by Prescott in Dubai

Construction progress

Legado at JVC by Prescott in Dubai construction updates

JVC · Prescott Real Estate Development L.L.C

Under constructionLast site inspection September 30, 2026 · 38 days ago
23.3%complete

When DLD first inspected the site on Aug 12, 2024, it was 0% complete. After 7 inspections it now stands at 23.3%.

That is about 0.9% more of the building completed each month on average.

First inspection · 0%Latest · 23.3%
Construction started
September 1, 2024
Completion date registered with DLD
August 31, 2027
Site inspections
7
Units
343
Escrow bank
United Bank Limited (Management Office)
DLD project no.
3210

Latest site photos

September 30, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 30, 2026

    3 months after the previous inspection

    +3.2%23.3%
  2. July 2, 2026

    3 months after the previous inspection

    +6.2%20.1%
  3. March 23, 2026

    3 months after the previous inspection

    +3.7%13.9%
  4. December 12, 2025

    3 months after the previous inspection

    +4.3%10.2%
  5. September 18, 2025

    4 months after the previous inspection

    +3.9%5.8%
  6. May 24, 2025

    9 months after the previous inspection

    +1.9%1.9%
  7. August 12, 2024

    First inspection

    0%

Thinking about Legado at JVC by Prescott in Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3210), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.