Legacy at Arjan by Sunrise

Construction progress

Legacy at Arjan by Sunrise construction updates

Arjan Dubai · Sunrise Capital Real Estate Development L.L.C

CompletedLast site inspection July 9, 2024 · 2 years ago
100%complete

DLD first inspected the site on Jul 4, 2023 at 35.7% complete, and recorded it as finished after 3 inspections, the last on Jul 9, 2024.

First inspection · 35.7%Latest · 100%
Construction started
October 22, 2022
Completion date registered with DLD
May 15, 2024
Site inspections
3
Units
132
Escrow bank
Mashreq Bank Psc
DLD project no.
2632

Latest site photos

July 9, 2024

Progress over time

Progress over time
0%25%50%75%100%2024

Inspection history

  1. July 9, 2024

    7 months after the previous inspection

    +35%100%
  2. November 30, 2023

    5 months after the previous inspection

    +29.3%65%
  3. July 4, 2023

    First inspection

    35.7%

Thinking about Legacy at Arjan by Sunrise?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2632), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat