Le Blanc by Imtiaz

Construction progress

Le Blanc by Imtiaz construction updates

Dubailand · Imtiaz Cove Real Estate Development L.L.C

Under constructionLast site inspection October 8, 2026 · 30 days ago
6%complete

When DLD first inspected the site on Oct 23, 2025, it was 0% complete. After 4 inspections it now stands at 6%.

That is about 0.5% more of the building completed each month on average.

First inspection · 0%Latest · 6%
Construction started
January 15, 2026
Completion date registered with DLD
October 15, 2028
Site inspections
4
Units
323
Escrow bank
Ajman Bank /P.J.S.C
DLD project no.
4174

Latest site photos

October 8, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. October 8, 2026

    3 months after the previous inspection

    +2.5%6%
  2. July 7, 2026

    3 months after the previous inspection

    +3%3.4%
  3. April 8, 2026

    5 months after the previous inspection

    +0.4%0.4%
  4. October 23, 2025

    First inspection

    0%

Thinking about Le Blanc by Imtiaz?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4174), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat