Lazord By Lapis Properties at Majan

Construction progress

Lazord By Lapis Properties at Majan construction updates

Majan · Lapis Properties L.L.C

Under constructionLast site inspection September 3, 2026 · 2 months ago
27.6%complete

When DLD first inspected the site on Jul 31, 2024, it was 0% complete. After 6 inspections it now stands at 27.6%.

That is about 1.1% more of the building completed each month on average.

First inspection · 0%Latest · 27.6%
Construction started
January 1, 2025
Completion date registered with DLD
December 31, 2026
Site inspections
6
Units
313
Escrow bank
Mashreq Bank Psc
DLD project no.
3209

Latest site photos

September 3, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 3, 2026

    4 months after the previous inspection

    +14.6%27.6%
  2. April 30, 2026

    3 months after the previous inspection

    +5.1%13.1%
  3. February 9, 2026

    5 months after the previous inspection

    +5.6%8%
  4. September 8, 2025

    4 months after the previous inspection

    +2.2%2.4%
  5. May 8, 2025

    9 months after the previous inspection

    +0.2%0.2%
  6. July 31, 2024

    First inspection

    0%

Thinking about Lazord By Lapis Properties at Majan?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3209), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.