Laya Courtyard at Dubai Studio City

Construction progress

Laya Courtyard at Dubai Studio City construction updates

Dubai Studio City · Laya Developers L.L.C

Under constructionLast site inspection September 15, 2026 · 2 months ago
50.6%complete

When DLD first inspected the site on Feb 13, 2024, it was 0% complete. After 5 inspections it now stands at 50.6%.

That is about 1.6% more of the building completed each month on average.

First inspection · 0%Latest · 50.6%
Construction started
October 1, 2023
Completion date registered with DLD
December 26, 2026
Site inspections
5
Units
289
Buildings
2
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2871

Latest site photos

September 15, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 15, 2026

    6 months after the previous inspection

    +13.6%50.6%
  2. March 23, 2026

    3 months after the previous inspection

    +6.3%36.9%
  3. December 15, 2025

    4 months after the previous inspection

    +11.8%30.6%
  4. August 28, 2025

    18 months after the previous inspection

    +18.8%18.8%
  5. February 13, 2024

    First inspection

    0%

Thinking about Laya Courtyard at Dubai Studio City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2871), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.