Lacina Residences at Ghaf Woods Phase 2

Construction progress

Lacina Residences at Ghaf Woods Phase 2 construction updates

Ghaf Woods · Majid Al Futtaim Ghaf Woods L.L.C

Under constructionLast site inspection November 3, 2026 · 4 days ago
30.4%complete

When DLD first inspected the site on Oct 17, 2024, it was 0% complete. After 6 inspections it now stands at 30.4%.

That is about 1.2% more of the building completed each month on average.

First inspection · 0%Latest · 30.4%
Construction started
December 1, 2024
Completion date registered with DLD
December 30, 2027
Site inspections
6
Units
324
Buildings
3
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
3336

Latest site photos

November 3, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. November 3, 2026

    4 months after the previous inspection

    +9.6%30.4%
  2. July 6, 2026

    3 months after the previous inspection

    +8.3%20.8%
  3. April 2, 2026

    4 months after the previous inspection

    +4%12.5%
  4. December 8, 2025

    0 days after the previous inspection

    8.5%
  5. December 8, 2025

    14 months after the previous inspection

    +8.5%8.5%
  6. October 17, 2024

    First inspection

    0%

Thinking about Lacina Residences at Ghaf Woods Phase 2?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3336), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.