Kyoto By ORO24

Construction progress

Kyoto By ORO24 construction updates

Arjan Dubai · Oro24 Real Estate Development L.L.C

Under constructionLast site inspection September 11, 2026 · 2 months ago
17%complete

When DLD first inspected the site on Jun 23, 2023, it was 0% complete. After 6 inspections it now stands at 17%.

That is about 0.4% more of the building completed each month on average.

First inspection · 0%Latest · 17%
Construction started
June 20, 2023
Completion date registered with DLD
September 20, 2026
Site inspections
6
Units
708
Escrow bank
Zand Bank P.J.S.C
DLD project no.
2702

Latest site photos

September 11, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. September 11, 2026

    6 months after the previous inspection

    +9.3%17%
  2. March 2, 2026

    7 months after the previous inspection

    +2.3%7.7%
  3. July 24, 2025

    5 months after the previous inspection

    +2.5%5.4%
  4. February 11, 2025

    15 months after the previous inspection

    +2.8%2.9%
  5. October 31, 2023

    4 months after the previous inspection

    +0%0%
  6. June 23, 2023

    First inspection

    0%

Thinking about Kyoto By ORO24?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2702), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.