Construction progress
Creek Dubai · Swiss Property Development L.L.C
DLD first inspected the site on Sep 14, 2017 at 5% complete, and recorded it as finished after 17 inspections, the last on Nov 18, 2025.
November 18, 2025
2 months after the previous inspection
4 months after the previous inspection
4 months after the previous inspection
4 months after the previous inspection
3 months after the previous inspection
4 months after the previous inspection
4 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
15 days after the previous inspection
14 days after the previous inspection
3 months after the previous inspection
19 months after the previous inspection
36 months after the previous inspection
6 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 1860), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.