Karma Residences at Liwan Dubailand

Construction progress

Karma Residences at Liwan Dubailand construction updates

Dubailand · Clear Vision Real Estate Development L.L.C

CompletedLast site inspection January 6, 2025 · 2 years ago
100%complete

DLD first inspected the site on Jan 26, 2024 at 0% complete, and recorded it as finished after 5 inspections, the last on Jan 6, 2025.

First inspection · 0%Latest · 100%
Construction started
September 14, 2023
Site inspections
5
Units
90
Escrow bank
The National Bank Of Fujairah P S C
DLD project no.
2934

Latest site photos

January 6, 2025

Progress over time

Progress over time
0%25%50%75%100%2025

Inspection history

  1. January 6, 2025

    25 days after the previous inspection

    +3.2%100%
  2. December 12, 2024

    2 months after the previous inspection

    +6.7%96.8%
  3. October 16, 2024

    5 months after the previous inspection

    +54.7%90%
  4. May 6, 2024

    3 months after the previous inspection

    +35.3%35.3%
  5. January 26, 2024

    First inspection

    0%

Thinking about Karma Residences at Liwan Dubailand?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2934), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.