Jumeirah Living Business Bay

Construction progress

Jumeirah Living Business Bay construction updates

Business Bay · Select Global Development L.L.C

CompletedLast site inspection December 16, 2025 · 11 months ago
100%complete

DLD first inspected the site on Feb 9, 2023 at 5.3% complete, and recorded it as finished after 8 inspections, the last on Dec 16, 2025.

First inspection · 5.3%Latest · 100%
Construction started
June 24, 2022
Completion date registered with DLD
June 14, 2025
Site inspections
8
Units
82
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
2436

Latest site photos

December 16, 2025

Progress over time

Progress over time
0%25%50%75%100%20242025

Inspection history

  1. December 16, 2025

    4 months after the previous inspection

    +9.3%100%
  2. August 21, 2025

    5 months after the previous inspection

    +17.8%90.7%
  3. March 27, 2025

    5 months after the previous inspection

    +22.4%72.9%
  4. October 30, 2024

    4 months after the previous inspection

    +25.9%50.5%
  5. June 25, 2024

    6 months after the previous inspection

    +10.5%24.6%
  6. January 3, 2024

    5 months after the previous inspection

    +4.9%14.1%
  7. August 15, 2023

    6 months after the previous inspection

    +3.9%9.2%
  8. February 9, 2023

    First inspection

    5.3%

Thinking about Jumeirah Living Business Bay?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2436), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.