Jannat by Deyaar

Construction progress

Jannat by Deyaar construction updates

Jumeirah Golf Estates · Deyaar Development (P.J.S.C)

CompletedLast site inspection April 8, 2026 · 7 months ago
100%complete

DLD first inspected the site on Jul 17, 2023 at 0% complete, and recorded it as finished after 7 inspections, the last on Apr 8, 2026.

First inspection · 0%Latest · 100%
Construction started
December 1, 2023
Site inspections
7
Units
362
Buildings
17
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
2725

Latest site photos

April 8, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. April 8, 2026

    2 months after the previous inspection

    +3.9%100%
  2. February 6, 2026

    4 months after the previous inspection

    +16.2%96.1%
  3. October 14, 2025

    4 months after the previous inspection

    +23.5%79.9%
  4. June 2, 2025

    4 months after the previous inspection

    +25.5%56.4%
  5. February 7, 2025

    6 months after the previous inspection

    +22.2%31%
  6. July 25, 2024

    12 months after the previous inspection

    +8.8%8.8%
  7. July 17, 2023

    First inspection

    0%

Thinking about Jannat by Deyaar?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2725), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.