Construction progress
Dubai Production City · Imperial 55 Real Estate Development L.L.C
When DLD first inspected the site on Oct 7, 2024, it was 0% complete. After 7 inspections it now stands at 43%.
That is about 2.9% more of the building completed each month on average.
January 5, 2026
0 days after the previous inspection
0 days after the previous inspection
7 months after the previous inspection
3 months after the previous inspection
25 days after the previous inspection
4 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 3217), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.