Imperial Residence at Dubai Production City

Construction progress

Imperial Residence at Dubai Production City construction updates

Dubai Production City · Imperial 55 Real Estate Development L.L.C

Under constructionLast site inspection January 5, 2026 · 10 months ago
43%complete

When DLD first inspected the site on Oct 7, 2024, it was 0% complete. After 7 inspections it now stands at 43%.

That is about 2.9% more of the building completed each month on average.

First inspection · 0%Latest · 43%
Construction started
June 1, 2024
Completion date registered with DLD
April 30, 2026
Site inspections
7
Units
137
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
3217

Latest site photos

January 5, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. January 5, 2026

    0 days after the previous inspection

    43%
  2. January 5, 2026

    0 days after the previous inspection

    43%
  3. January 5, 2026

    7 months after the previous inspection

    +22.2%43%
  4. June 2, 2025

    3 months after the previous inspection

    +6.4%20.8%
  5. February 17, 2025

    25 days after the previous inspection

    +2.2%14.4%
  6. January 23, 2025

    4 months after the previous inspection

    +12.2%12.2%
  7. October 7, 2024

    First inspection

    0%

Thinking about Imperial Residence at Dubai Production City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3217), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.