Hyde Walk Residence at Al Satwa Dubai

Construction progress

Hyde Walk Residence at Al Satwa Dubai construction updates

Al Satwa Dubai · Imtiaz Real Estate Investment & Development L.L.C

CompletedLast site inspection November 17, 2025 · 12 months ago
100%complete

DLD first inspected the site on Nov 22, 2023 at 0% complete, and recorded it as finished after 5 inspections, the last on Nov 17, 2025.

First inspection · 0%Latest · 100%
Construction started
December 15, 2023
Site inspections
5
Units
89
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2860

Latest site photos

November 17, 2025

Progress over time

Progress over time
0%25%50%75%100%20242025

Inspection history

  1. November 17, 2025

    39 days after the previous inspection

    +1.4%100%
  2. October 9, 2025

    4 months after the previous inspection

    +23.6%98.6%
  3. June 22, 2025

    4 months after the previous inspection

    +34.3%74.9%
  4. February 7, 2025

    15 months after the previous inspection

    +40.7%40.7%
  5. November 22, 2023

    First inspection

    0%

Thinking about Hyde Walk Residence at Al Satwa Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2860), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat