Holland Gardens at Town Square Dubai by Nshama

Construction progress

Holland Gardens at Town Square Dubai by Nshama construction updates

Town Square · Nshama Properties Owned By Nshmi Development One Person Company L.L.C

CompletedLast site inspection November 11, 2025 · 12 months ago
100%complete

DLD first inspected the site on Nov 29, 2022 at 0% complete, and recorded it as finished after 9 inspections, the last on Nov 11, 2025.

First inspection · 0%Latest · 100%
Construction started
September 15, 2024
Completion date registered with DLD
September 30, 2025
Site inspections
9
Units
228
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2526

Latest site photos

November 11, 2025

Progress over time

Progress over time
0%25%50%75%100%202320242025

Inspection history

  1. November 11, 2025

    4 months after the previous inspection

    +21.3%100%
  2. July 3, 2025

    4 months after the previous inspection

    +23.2%78.8%
  3. March 13, 2025

    2 months after the previous inspection

    +9.8%55.5%
  4. January 14, 2025

    4 months after the previous inspection

    +13.5%45.7%
  5. September 4, 2024

    3 months after the previous inspection

    +21.6%32.2%
  6. June 7, 2024

    2 months after the previous inspection

    +6.5%10.6%
  7. March 26, 2024

    7 months after the previous inspection

    +4.1%4.1%
  8. August 14, 2023

    8 months after the previous inspection

    0%
  9. November 29, 2022

    First inspection

    0%

Thinking about Holland Gardens at Town Square Dubai by Nshama?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2526), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.