Hillcrest at Town Square Dubai

Construction progress

Hillcrest at Town Square Dubai construction updates

Town Square · Nshama Properties Owned By Nshmi Development One Person Company L.L.C

Under constructionLast site inspection September 17, 2026 · 2 months ago
38.4%complete

When DLD first inspected the site on Aug 6, 2024, it was 0% complete. After 5 inspections it now stands at 38.4%.

That is about 1.5% more of the building completed each month on average.

First inspection · 0%Latest · 38.4%
Construction started
March 3, 2025
Completion date registered with DLD
June 30, 2027
Site inspections
5
Units
171
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3211

Latest site photos

September 17, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 17, 2026

    5 months after the previous inspection

    +20.1%38.4%
  2. April 30, 2026

    4 months after the previous inspection

    +7.3%18.3%
  3. January 9, 2026

    0 days after the previous inspection

    11%
  4. January 9, 2026

    17 months after the previous inspection

    +11%11%
  5. August 6, 2024

    First inspection

    0%

Thinking about Hillcrest at Town Square Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3211), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.