Havelock Residences at Al Furjan, Dubai

Construction progress

Havelock Residences at Al Furjan, Dubai construction updates

Al Furjan · Aa And Hmb Real Estate Development L.L.C

Under constructionLast site inspection July 6, 2026 · 4 months ago
11.4%complete

When DLD first inspected the site on Jul 31, 2024, it was 0% complete. After 5 inspections it now stands at 11.4%.

That is about 0.5% more of the building completed each month on average.

First inspection · 0%Latest · 11.4%
Construction started
October 1, 2024
Completion date registered with DLD
December 31, 2026
Site inspections
5
Units
230
Escrow bank
United Bank Limited (Management Office)
DLD project no.
3213

Latest site photos

July 6, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. July 6, 2026

    3 months after the previous inspection

    +5.6%11.4%
  2. March 27, 2026

    6 months after the previous inspection

    +1.1%5.8%
  3. October 6, 2025

    5 months after the previous inspection

    +4.7%4.7%
  4. May 22, 2025

    10 months after the previous inspection

    +0%0%
  5. July 31, 2024

    First inspection

    0%

Thinking about Havelock Residences at Al Furjan, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3213), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.