Havelock Heights at JVC, Dubai

Construction progress

Havelock Heights at JVC, Dubai construction updates

JVC · Aa And Hmb Real Estate Development L.L.C

Under constructionLast site inspection October 8, 2026 · 30 days ago
40%complete

When DLD first inspected the site on Jun 12, 2024, it was 0% complete. After 6 inspections it now stands at 40%.

That is about 1.4% more of the building completed each month on average.

First inspection · 0%Latest · 40%
Construction started
September 15, 2024
Completion date registered with DLD
September 15, 2026
Site inspections
6
Units
156
Escrow bank
United Bank Limited (Management Office)
DLD project no.
3135

Latest site photos

October 8, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 8, 2026

    3 months after the previous inspection

    +12%40%
  2. June 25, 2026

    3 months after the previous inspection

    +9.2%28%
  3. March 18, 2026

    5 months after the previous inspection

    +9.4%18.8%
  4. October 7, 2025

    5 months after the previous inspection

    +3.9%9.4%
  5. May 22, 2025

    11 months after the previous inspection

    +5.5%5.5%
  6. June 12, 2024

    First inspection

    0%

Thinking about Havelock Heights at JVC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3135), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.