Harbour Lights by Damac at Dubai Maritime City

Construction progress

Harbour Lights by Damac at Dubai Maritime City construction updates

Dubai Maritime City · Damac J W F Investment L.L.C

Under constructionLast site inspection July 9, 2026 · 4 months ago
64.3%complete

When DLD first inspected the site on Nov 21, 2022, it was 0% complete. After 9 inspections it now stands at 64.3%.

That is about 1.5% more of the building completed each month on average.

First inspection · 0%Latest · 64.3%
Construction started
February 16, 2023
Completion date registered with DLD
May 21, 2027
Site inspections
9
Units
297
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
2516

Latest site photos

July 9, 2026

Progress over time

Progress over time
0%25%50%75%100%2023202420252026

Inspection history

  1. July 9, 2026

    4 months after the previous inspection

    +11.4%64.3%
  2. March 17, 2026

    4 months after the previous inspection

    +17%52.9%
  3. November 19, 2025

    4 months after the previous inspection

    +10.4%35.9%
  4. July 7, 2025

    5 months after the previous inspection

    +7.9%25.5%
  5. January 21, 2025

    7 months after the previous inspection

    +9.3%17.6%
  6. July 5, 2024

    7 months after the previous inspection

    +4.2%8.4%
  7. November 30, 2023

    4 months after the previous inspection

    +2.2%4.2%
  8. July 20, 2023

    8 months after the previous inspection

    +2%2%
  9. November 21, 2022

    First inspection

    0%

Thinking about Harbour Lights by Damac at Dubai Maritime City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2516), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.