Hadley Heights at Jumeirah Village Circle (JVC)

Construction progress

Hadley Heights at Jumeirah Village Circle (JVC) construction updates

JVC · Leos Development L.L.C

CompletedLast site inspection October 1, 2025 · 13 months ago
100%complete

DLD first inspected the site on Feb 7, 2023 at 0% complete, and recorded it as finished after 8 inspections, the last on Oct 1, 2025.

First inspection · 0%Latest · 100%
Construction started
May 1, 2023
Completion date registered with DLD
November 30, 2025
Site inspections
8
Units
219
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2563

Latest site photos

October 1, 2025

Progress over time

Progress over time
0%25%50%75%100%20242025

Inspection history

  1. October 1, 2025

    5 days after the previous inspection

    100%
  2. September 26, 2025

    8 months after the previous inspection

    +24.9%100%
  3. January 21, 2025

    4 months after the previous inspection

    +25%75.1%
  4. October 4, 2024

    4 months after the previous inspection

    +18.6%50.1%
  5. June 19, 2024

    6 months after the previous inspection

    +20.5%31.6%
  6. December 18, 2023

    4 months after the previous inspection

    +4.9%11%
  7. August 22, 2023

    6 months after the previous inspection

    +6.1%6.1%
  8. February 7, 2023

    First inspection

    0%

Thinking about Hadley Heights at Jumeirah Village Circle (JVC)?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2563), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat