Grove by Nshama at Town Square Park Dubai

Construction progress

Grove by Nshama at Town Square Park Dubai construction updates

Town Square · Nshama Properties Owned By Nshmi Development One Person Company L.L.C

Under constructionLast site inspection September 15, 2026 · 2 months ago
40.7%complete

When DLD first inspected the site on Dec 12, 2023, it was 0% complete. After 8 inspections it now stands at 40.7%.

That is about 1.2% more of the building completed each month on average.

First inspection · 0%Latest · 40.7%
Construction started
May 20, 2024
Site inspections
8
Units
378
Buildings
2
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2850

Latest site photos

September 15, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. September 15, 2026

    5 months after the previous inspection

    +25.2%40.7%
  2. April 30, 2026

    4 months after the previous inspection

    +5.8%15.5%
  3. January 9, 2026

    9 months after the previous inspection

    +9.2%9.7%
  4. April 8, 2025

    4 months after the previous inspection

    +0.4%0.5%
  5. December 12, 2024

    0 days after the previous inspection

    0.1%
  6. December 12, 2024

    0 days after the previous inspection

    0.1%
  7. December 12, 2024

    12 months after the previous inspection

    +0.1%0.1%
  8. December 12, 2023

    First inspection

    0%

Thinking about Grove by Nshama at Town Square Park Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2850), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.