Greenway at Emaar South Dubai

Construction progress

Greenway at Emaar South Dubai construction updates

Emaar South · Emaar Dubai South Dwc Llc

Under constructionLast site inspection July 20, 2026 · 4 months ago
39.1%complete

When DLD first inspected the site on Apr 1, 2024, it was 0% complete. After 8 inspections it now stands at 39.1%.

That is about 1.4% more of the building completed each month on average.

First inspection · 0%Latest · 39.1%
Construction started
October 4, 2024
Site inspections
8
Units
232
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
3032

Latest site photos

July 20, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. July 20, 2026

    4 months after the previous inspection

    +6.8%39.1%
  2. March 17, 2026

    3 months after the previous inspection

    +9.1%32.3%
  3. December 12, 2025

    3 months after the previous inspection

    +8.4%23.2%
  4. September 19, 2025

    3 months after the previous inspection

    +7.8%14.8%
  5. June 25, 2025

    4 months after the previous inspection

    +6.8%7%
  6. March 7, 2025

    4 months after the previous inspection

    +0.2%0.2%
  7. November 4, 2024

    7 months after the previous inspection

    +0%0%
  8. April 1, 2024

    First inspection

    0%

Thinking about Greenway at Emaar South Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3032), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.