Greenway 2 at Emaar South Dubai

Construction progress

Greenway 2 at Emaar South Dubai construction updates

Emaar South · Emaar Dubai South Dwc Llc

Under constructionLast site inspection July 29, 2026 · 3 months ago
34.4%complete

When DLD first inspected the site on May 30, 2024, it was 0% complete. After 6 inspections it now stands at 34.4%.

That is about 1.3% more of the building completed each month on average.

First inspection · 0%Latest · 34.4%
Construction started
October 23, 2024
Completion date registered with DLD
May 31, 2028
Site inspections
6
Units
492
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
3121

Latest site photos

July 29, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. July 29, 2026

    3 months after the previous inspection

    +10.4%34.4%
  2. April 21, 2026

    6 months after the previous inspection

    +11%24%
  3. October 16, 2025

    4 months after the previous inspection

    +8.6%13%
  4. June 12, 2025

    6 months after the previous inspection

    +2.9%4.4%
  5. December 16, 2024

    7 months after the previous inspection

    +1.5%1.5%
  6. May 30, 2024

    First inspection

    0%

Thinking about Greenway 2 at Emaar South Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3121), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.