Greenville at Emaar South, Dubai

Construction progress

Greenville at Emaar South, Dubai construction updates

Emaar South · Emaar Dubai South Dwc Llc

Under constructionLast site inspection May 14, 2026 · 6 months ago
46%complete

When DLD first inspected the site on Sep 27, 2024, it was 0% complete. After 5 inspections it now stands at 46%.

That is about 2.4% more of the building completed each month on average.

First inspection · 0%Latest · 46%
Construction started
January 30, 2025
Completion date registered with DLD
March 31, 2029
Site inspections
5
Units
140
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
3316

Latest site photos

May 14, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. May 14, 2026

    4 months after the previous inspection

    +16%46%
  2. January 26, 2026

    4 months after the previous inspection

    +22.2%30%
  3. October 8, 2025

    5 months after the previous inspection

    +6.9%7.9%
  4. May 12, 2025

    7 months after the previous inspection

    +1%1%
  5. September 27, 2024

    First inspection

    0%

Thinking about Greenville at Emaar South, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3316), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.