Greenville 2 at Emaar South, Dubai

Construction progress

Greenville 2 at Emaar South, Dubai construction updates

Emaar South · Emaar Dubai South Dwc Llc

Under constructionLast site inspection July 19, 2026 · 4 months ago
47.3%complete

When DLD first inspected the site on Sep 27, 2024, it was 0% complete. After 6 inspections it now stands at 47.3%.

That is about 2.2% more of the building completed each month on average.

First inspection · 0%Latest · 47.3%
Construction started
January 30, 2025
Completion date registered with DLD
March 31, 2029
Site inspections
6
Units
148
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
3319

Latest site photos

July 19, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. July 19, 2026

    4 months after the previous inspection

    +16.1%47.3%
  2. March 30, 2026

    3 months after the previous inspection

    +11.7%31.2%
  3. December 31, 2025

    4 months after the previous inspection

    +13.1%19.5%
  4. September 11, 2025

    4 months after the previous inspection

    +5.8%6.4%
  5. May 13, 2025

    7 months after the previous inspection

    +0.6%0.6%
  6. September 27, 2024

    First inspection

    0%

Thinking about Greenville 2 at Emaar South, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3319), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.